Slab Or Floor System
Step 10. The concreting of the slab or floor system.


Quick Check List Before Concreting
- House has been sighted in correct position on block.
- Drainer has completed all under slab drainage with aproval.
- Piers and thickening beams.
- Under slab termite protection.
- Polythene waterproof membrane - all joints must be taped together.
- All reinforcing steel.
- Accurate formwork dimensions.
Care must be taken not to puncture the waterproof membrane and any holes must be taped. Be sure to check that the pest control agent has sprayed the floor area before laying the waterproof membrane. A poison certificate must be obtained to satisfy the local council.

Suspended Steel Floor System
Structural floor frame drawings will be supplied giving set out positions of stumps, bearers and joists, veranda and landing positions where applicable. Your home will be delivered in stages as work is completed, at this stage you should have received at minimum your joists, bearers and floor boards as well as any footing posts and fixing plates.


Owner Builder
Diy Kit Homes
Cheapest Real Estate
Contact Details
Owner Builder Australia